Nov 22, 2023
Enchanted Oaks Sewer Blockage cleared on 11/21 at 6p
The Enchanted oaks sewage blockage has been cleared as of Tuesday, 11/21 at 6p. MOC is replacing manhole covers now and should be done...
Nov 21, 2023
Update on the sewer blockage in Enchanted Oaks area - 11/21/23 @ 2:45p
MOC has located the blockage and is awaiting a jet truck to arrive to take care of the blockage. ETA is hopefully within the next two...
Nov 21, 2023
Sewer Line Blockage issue - 11/21/23
A sewer blockage was identified in the Enchanted Oaks area on Monday, 11/20 in the late afternoon. MOC and District engineers are working...
Nov 8, 2023
Updates for Enchanted Oaks Sewer Rehab Project - 11/8/23
An update has been added to the District website under Important Notices related to the sewer rehab project in Enchanted Oaks. A new map...
Nov 7, 2023
WCID110 No Longer under Drought Restrictions effective Tues., Nov. 11
NHCRWA terminates Stage 1 of the Drought Contingency Plan The North Harris County Regional Water Authority is immediately terminating...